Approve Modification No. 1 to Contract No. 4400007520 with Reliance Architecture, LLC, in the amount of $634,670.00, for the ADA Transition Plan for Retrofits. (Facilities Management Department) (Commissioner Travillion)
Staff Report & Agenda Item Details
This contract provided consulting services during Phase I of this project to investigate the ADA List of Report Items and their referenced deficiencies within twelve (12) locations. The ADA List of Report Items provided a breakdown of items that the consultant investigated and determined which items were feasible to correct and which were not.<br><br>Contract Modification No. 1 is for Phase II of this project for the production of construction documents consisting of the additional eight (8) Work Products; Site Survey, Schematic Design, Site Permitting, Design Development, Construction Drawings, Building Permitting, Bidding and Construction Administration for six (6) of the twelve (12) locations investigated in Phase I. This modification will increase the total contract value by $634,670.00 from $210,000.00 to $844,670.00, an aggregate increase of 302.22% from the original contract amount.<br><br><strong>Contract Information: </strong><br>Contract No.: 4400007520<br>Contractor Name: Reliance Architecture, LLC<br>Contract Modification Amount: $634,670.00<br>Contract Period: Through completion<br><br><strong>Current Contract Expenditures:</strong> <br>Within the last 12 months, $210,000.00 has been spent against this contract.<br><br><strong>Previous Contract and Modification Activity:</strong><br>On May 13, 2025, the Commissioners Court approved the initial contract in the amount of $210,000.00.